Liverpool's northern waterfront is getting a reset. On 24 November 2026, Liverpool City Council approved sweeping changes to Peel Waters' £5.5bn Liverpool Waters masterplan, the 60-hectare docklands scheme north of the Pier Head that first won outline consent back in 2013. The revised plan cuts the maximum floorspace by around 8m sq ft. That reflects changing property demand, rising construction costs and the arrival of Everton's Hill Dickinson Stadium at Bramley-Moore Dock, which sits on land originally earmarked for housing. There's good news too: Peel has brought the main phase at Northern Docks, around the stadium, forward from 2036 to this decade.
So what's changed? The new framework allows up to 5,836 homes, 20% of them affordable. Add the 1,275 homes already brought forward under separate consents and the overall total drops from 9,000 to just over 7,100. Office space falls from about 3.4m sq ft to 1.25m sq ft, and shops, restaurants and bars shrink from 880,000 sq ft to under 280,000 sq ft. All basement parking goes, with the maximum number of spaces cut from 13,100 to 2,370. Several landmark towers have been lowered, but the tallest, at King Edward Triangle, keeps its 174m height limit. The plan covers five neighbourhoods and runs to 2041.
Work is already moving on the ground. Graham is delivering a £71m infrastructure package at Central Docks to unlock around 2,350 homes. It's part of an £81m programme backed by £55m from Homes England and £26m from Peel. The centrepiece is a five-acre waterfront park with more than 3,000 trees, due to open in spring 2028, and more than 1,300 tonnes of historic dock cobbles have been recovered for reuse. Peel Waters managing director James Whittaker said "Liverpool Waters is entering an exciting new chapter", and development director Chris Capes said the update creates "a more deliverable framework for future growth."